Getting Error "APP-GMF-87915: Adjustment Date Should Be Before Today's Date" For Lot Cost Adjustment In Current Period
(Doc ID 2305610.1)
Last updated on APRIL 04, 2025
Applies to:
Oracle Process Manufacturing Financials - Version 12.2.5 and laterInformation in this document applies to any platform.
Symptoms
On : 12.2.5 version, Lot Costs
When entering a lot cost adjustment in the current period with an adjustment date prior to today's date, the following error occurs. If an adjustment date from the prior period is entered, the lot cost adjustment can be created.
ERROR
-----------------------
APP-GMF-87915: Adjustment date should be before today's date (&SYSDATE). (REFDATE=)
STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Responsibility: OPM Financials
2. Navigation: Lot Cost > Lot Cost Adjustment
3. Make an adjustment with adjustment date prior to today's date and also within the current period.
Changes
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Changes |
Cause |
Solution |
References |