How to Restrict Move Order Generation for OPM Batch Picking When Not All Required Quantity is Available

(Doc ID 2310943.1)

Last updated on SEPTEMBER 25, 2017

Applies to:

Oracle Process Manufacturing Process Execution - Version 12.2.6 and later
Information in this document applies to any platform.

Goal

Batch Ingredient Picking and Move Order are still can be generated when item is not fully available.
Here is the problem scenario:
We create Batch Document with following material requirements

Product : FG1 Plan Qty = 10 kg
Ingredient
- RM1 Plan Qty = 5 kg
- RM2 Plan Qty = 3 kg
- RM3 Plan Qty = 4 kg

Current Available On Hand in warehouse : RM 1 = 20 kg, RM2=20 kg, RM3 only 1 kg ( shortage 3 kg from the requirement).
Then create Ingredient Picking for the Batch.
The system will generate Move Order Slip as follow :
RM1 = 5 kg
RM2= 3 kg
RM3 = 1 kg (the only onhand available).

For your information, our manufacturing is a Pharmaceutical/ Medicine. You cannot do the production process until both the ingredient items and the qty are fully fulfilled/available.
Question:
- How to restrict the Ingredient Picking process or MO generation when one or more both Ingredient Item or Quantity is shortage?
 

Solution

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms