'MTO'The planned start date or planned completion date, or both dates are outside the date range specified by the validity rule

(Doc ID 2312445.1)

Last updated on SEPTEMBER 29, 2017

Applies to:

Oracle Process Manufacturing Process Execution - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

On : 12.1.3 version, Batches

When attempting to create batch using MTO
the following error occurs.

ERROR
-----------------------
Message from Create_Batch API is The planned start date or planned completion date, or both dates are outside the date range specified by the validity rule


STEPS
-----------------------
The issue can be reproduced at will with the following steps:

1. Create the Sale order and book .

2. Run the Concurrent MTO .(Make to Order).



Cause