Symptoms

ACTUAL BEHAVIOR

There is a job in which required quantity for a component doesn't match with extended quantity calculated in the BOM of assembly.
In particular, looking at the job components' form, it is possibile to individuate the request of an unusually very large quantity for a specific component G40003961 (6456 pieces). While
examining the related extended BOM the required quantity is way lower (the sum of the extended quantities is 122, in line with the normal usage of that component for similar assemblies).

EXPECTED BEHAVIOR

We didn't understand how that quantity has been calculated by the system and which is the cause of the problem.

STEPS

The issue can be reproduced at will with the following steps:
1. Responsibility: Work In Process
2. Navigation: Discrete Job-> Discrete Job
3. Create job with problematic component.
4. See problematic component with large quantity.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms