Symptoms

On : 12.1.3 version, Status Reports

ACTUAL BEHAVIOR
---------------
Expenditure Type of Requisition in PA PSI form does not match the Expenditure Type of PO Requisition Line

A. PSI Commitment Form:
Commitment Number = 201001227
Comitment Type = Requisition
Quantity = 50
Approved = checked
Raw Cost = 18.50
Expenditure Type = Material Costs

B. REQUISITION form:
Number = 201001227
Status = Approved
Total = 1,816.27

=> Requisition Lines >> Requisition Distribution Lines:
Project = 222222222
Task = 1.011.011.100
Expenditure Type = 4.03.Piping materials

EXPECTED BEHAVIOR
-----------------------
The expenditure type should match for the same requisition.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
See above



Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.