User Accidentally Implemented Revised Item With Future Date On Change Order, Is there An Option To Change Effective Date To Current Date ?

(Doc ID 2318794.1)

Last updated on OCTOBER 24, 2017

Applies to:

Oracle Engineering - Version 12.1.3 and later
Oracle Product Hub - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

On : 12.1.3 version, ECO

A revised item change was accidentally implemented with the incorrect Effective 18-SEP-2018. This is far in the future, so the changes cannot be used.
Need to change the Effective Date of revised item from 18-SEP-2018 to Current Date , so that the changes are effective.

Cause

Sign In with your My Oracle Support account