CANNOT CLOSE OSP BATCH WHERE PO REQUISITION WAS CANCELED

(Doc ID 2321072.1)

Last updated on OCTOBER 27, 2017

Applies to:

Oracle Process Manufacturing Process Execution - Version 12.2.5 and later
Information in this document applies to any platform.

Symptoms

On : 12.2.5 version, Workbench

When attempting to close the OSP batch with Requisition cancelled
the following error occurs.

ERROR
-----------------------
There is no completed resource transaction for the osp step. Please run
resource manager concurrent program to import pending resource transaction in
the resource transaction open interface.


STEPS
-----------------------
The issue can be reproduced at will with the following steps:

1. Batch in Complete status .

2. Try to close the batch .

3. Error is thrown .

Cause