R12: PAXPREPR: Work Type Is Required In Project Task Details When The Profile Option 'PA: Require Work Type Entry for Expenditures' Is Set To No

(Doc ID 2323326.1)

Last updated on OCTOBER 31, 2017

Applies to:

Oracle Project Foundation - Version 12.2.6 and later
Information in this document applies to any platform.

Symptoms

After upgrading from 11.5.10 to 12.2.6, when users create a new task for a project, the 'Work Type' field is required. This field was not required before the upgrade.

The profile option 'PA: Require Work Type Entry for Expenditures' is set to 'No' at the site level.

Cause

Sign In with your My Oracle Support account