Unable To Baseline Project

(Doc ID 2326936.1)

Last updated on NOVEMBER 09, 2017

Applies to:

Oracle Grants Accounting - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

Unable to baseline a project in the awards budget screen after adding funds to an installment and project funding.

Changes

Added funding to the award installment and new project funding. Added a new budget amount at the task level.

Cause