R12 Primavera Integration With Projects - Workplan Structure Doesn't Update Properly

(Doc ID 2327548.1)

Last updated on NOVEMBER 13, 2017

Applies to:

Oracle Project Planning and Control - Version 12.2.4 and later
Information in this document applies to any platform.

Symptoms

User is using Primavera EPPM application to import the project & structure data to EBS Projects

The first time the information is created successfully, but when in Primavera the workplan structure is changed then the following behavior appears.

Changes done in Primavera:
 - the task structure has moved to a different parent and
 - the task and parent task number has been changed


ACTUAL BEHAVIOR
---------------
After the Project structure is changed in Primavera then in EBS Projects the Workplan structure is not synchronized. The workplan break down structure is different than in P6.

EXPECTED BEHAVIOR
-----------------------
After the Project structure is changed in Primavera then on EBS Projects the Workplan structure should be not synchronized with P6



Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms