Goal

At capitalization of CIP assets business needs to split cost to various categories.  How can this be achieved?

Ex.  All Charges are collected under 1 CIP Asset in BUILDING category.
At capitalization the charges need split to 3 different Asset Categories:
Building
Equipment
Furniture & Fixtures

Resulting in 3 Asset treated under the various category defaults (method/life)

 

Solution

To view full details, sign in with your My Oracle Support account.