Two Step Delinking Process To Realign Funds On The Same Mod Causes Error

(Doc ID 2338604.1)

Last updated on DECEMBER 18, 2017

Applies to:

Oracle Contract Lifecycle Management for Public Sector - Version 12.2.6 and later
Information in this document applies to any platform.

Symptoms

Using Purchasing, Version 12.2.6

Actual:
Testing Two step delinking process to realign funds on the same Mod resulted in error.

Expected:
Testing Two step delinking process to realign funds on the same Mod should not error.


Replication Steps:
Testing Two step delinking process to realign funds on the same Mod resulted in error.
1. From a CLM Purchasing responsibility, create award with one line from a Req in the DWB so the line distribution references a PR. You will also need another PR Line Item from another PR for the same amount for the modification
2. Create a modification to the award
3. Complete header required fields and navigate to Line Items
4. Select the LI and then select Unlink Requisitions and click Go. System presents message that the LI is unlinked and removes the Distribution
5. Select the same LI and then select Link to Request Lines and click Go
6. Navigate the screens to find the other req line from Step 1 and link it
7. Receive error.

Unable to complete process for realigning funds in the same modification action. Log files attached.




Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms