Issue with Date Format on the Solicitation Pdf

(Doc ID 2341120.1)

Last updated on DECEMBER 19, 2017

Applies to:

Oracle Contract Lifecycle Management for Public Sector - Version 12.2.4 and later
Information in this document applies to any platform.

Symptoms

On Contract Lifecycle Management (CLM) 12.2.4 after applying patch 26912205, Date printed on Solicitation PDF is showing in the incorrect format (ex. 2017-11-14)

Date should be in the correct format (ex. 11/03/2017)

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Open a Solicitation PDF
2. View the Offer Due Date
3. Can see the format is incorrect


Due to this issue, users cannot get the correct time format on the solicitation PDF

Cause