R12.2: Project Financial Plans: View By Period - No Values Populated For SubTasks

(Doc ID 2350307.1)

Last updated on JANUARY 18, 2018

Applies to:

Oracle Project Planning and Control - Version 12.2.6 and later
Information in this document applies to any platform.

Symptoms

Upgraded from 12.1.3 to 12.2.x:

Project - Financial Plans - View by period - No value populated in task level. All values displaying in contract level.

In 12.1.3 - its populate both is contract and task level.

Steps:

======

1. From release 12.1.3:

Financial >> Budgets and Forecasts page:
View Plan: Project Budget page:
View by = Period
Display Periods stating = 13-12

Element Name
-----------------------------------------
National Centre - F, F & E (117444)
Stage 6 (Stage 6)
Office Furniture (6.2)
B1 Furniture (6.2.1)
B2 Furniture (6.2.2)
B3 Furniture (6.2.3)
B4 Furniture (6.2.4)
Street Furniture (6.2.5)

==> For B1 Furniture (6.2.1), Amount shows 1,217,521.00

From Release 12.2.x:
Project = 117444

Financial >> Budgets and Forecasts page:
View Plan: Project Budget page:
View by = Period
Display periods stating = 5-13

Element Name
-----------------------------------------
National Centre - F, F & E (117444)
Stage 6 (Stage 6)
Office Furniture (6.2)
B1 Furniture (6.2.1)
B2 Furniture (6.2.2)
B3 Furniture (6.2.3)
B4 Furniture (6.2.4)
Street Furniture (6.2.5)

==> From B1 Furniture (6.2.1) going down, amount shows 0.00 for all.  This is the issue.

 

 

 

 

 

 

 

 

Changes

 Upgraded fro 12.1.3 to 12.2.x

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms