How to Keep Rebuildable Item Cost As Sum of Its Component Costs ?

(Doc ID 2355375.1)

Last updated on JANUARY 31, 2018

Applies to:

Oracle Cost Management - Version 12.1.1 and later
Oracle Enterprise Asset Management - Version 12.1.1 and later
Oracle Work in Process - Version 12.1.1 and later
Information in this document applies to any platform.

Goal

Can we add the costs to an assembly for EAM with below scenario?

We have the following case
Item A is engine which , this engine has component of spare parts X, Y and Z
What we need is :
1- Create Item A and its component X, Y and Z
2- Create WO for the item A
3- Assign the materials X, Y and Z to the WO
4- Issue the materials
5- Update the item cost in the store with the sum of items cost X, Y and Z
Is this applicable to be achieved with standard or even using workaround?
Could you please help to try this case
 

Solution

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms