'APP-GME-82528'-Actual dates of for the operation do not fall in the range of batch step actual dates

(Doc ID 2356062.1)

Last updated on FEBRUARY 10, 2018

Applies to:

Oracle Process Manufacturing Process Execution - Version 12.2.4 and later
Information in this document applies to any platform.

Goal

On : 12.2.4 version, Batches

Unable to change the Batch step actual date to future dates

When try to change to future date , error is thrown :

APP-GME-82528-Actual dates of for the operation do not fall in the range of batch step actual dates

Would it be possible to allow to enter a later date also? We don’t see any reason why this should not be allowed ?

Solution

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms