R12: PJRM: Unable to Delete the Team Role as "Project Manager" from PRM Project Assignments

(Doc ID 2357052.1)

Last updated on FEBRUARY 22, 2018

Applies to:

Oracle Project Resource Management - Version 12.1.3 and later
Information in this document applies to any platform.

Goal

A project has a project duration from e.g., '11-Nov-17' to '30-Mar-2018'. Initially, Project Manager (person X) was assigned to the
project from the project start date and without end date.

Later on, a new Project Resource Management (PRM) assignment for team role 'Project Manager' was created (for person Y),  with assignment starting '04-Dec-2017' and ending '30-Mar-2018'.

The system allowed the assignment to be created. Due to this assignment, the earlier Project Manager (person X) for the project was end-dated on 03-DEC-2017 and new Project Manager assigned to the project starting 04-Dec-2017 to the project end date.

This second assignment was a mistake and should not have been created. Users want the assignment to be deleted and to make the PM the person who was initially assigned (person X).

Tried modifying the Project Manager, but system allowed  neither update to the Project Manager for the project nor deletion of the PRM assignment.

How can this be corrected?

 

Solution

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms