R12: PO Is Not Getting Approved As Project Budget Is Not Approved

(Doc ID 2360068.1)

Last updated on MARCH 30, 2018

Applies to:

Oracle Project Costing - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

As per the standard functionality, the PO should get approved as there are no budgetary controls involved in the project.
A PO against that project it is not getting approved and showing error:
ERROR
  Budget is not Approved.


Cause