Symptoms

ACTUAL BEHAVIOR
---------------
When attempting to add an employee as task manager in Microsoft Project (MSP),
via the standard 'receive list of values from oracle projects' function, the
selected employee is not passed back to MSP, i.e. the task manager field
remains blank.

This behaviour is replicated in other fields where value is selected from list, e.g. Task Service Type.


STEPS
-----------------------
1. Go to Microsoft Project Integration Installation Install MSP Integration

2. Receive project : Switch to Oracle Financial Gantt

3. Go to Task Manager

4. Go to menu: Receive From Oracle Projects -> List of values

5. Select 'Task Manager' from the search result

6. Filed is marked black

6. Data not populated for 'Task Manager' column.

 

Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.