Symptoms

When enter the Physical Percent Complete manually in the Workplan at the lowest task level the system will rollup to the top task leve on the Workplan.

But the same is not copying to the Financial plan when the "Physical % Complete" is updated from the Workplan.


ACTUAL BEHAVIOR
----------------------------
On Financial tab > "Physical % Complete" is not updated
as per Workplan > Tasks > Physical Percent Complete

EXPECTED BEHAVIOR
-----------------------
"Physical % Complete" from Financial tab should be updated with the values
as per Workplan > Tasks > Physical Percent Complete



Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.