R12 Why On the Budget Form - Budgetary Controls The Control Level Is None But The Controls Are Defined On Project Type and Project Template ?

(Doc ID 2372671.1)

Last updated on MARCH 12, 2018

Applies to:

Oracle Project Costing - Version 12.2.4 and later
Information in this document applies to any platform.

Goal

Why on the Budget form > Budgetary Controls the control level is none for Project and Task ?
even if the budgetary controls are defined at Project Type and Project Template level.

 