Orders are not Consolidated into One Shipment When ORDER MOVEMENT GROUPING TYPE Parameter Set to 'With Start Date'

(Doc ID 2384218.1)

Last updated on APRIL 13, 2018

Applies to:

Oracle Transportation Operational Planning - Version 6.4.2 and later
Information in this document applies to any platform.

Symptoms

Within network routing, when planning order movements with planning parameter ORDER MOVEMENT GROUPING TYPE set to "With Start Date", order movements are formed into groups "With Start Date" before any order movement group has been
planned, resulting in the start date data being premature.