Symptoms

On : 12.2.4 version, WIP Costing

ACTUAL BEHAVIOR
---------------
Supply Chain Cost Rollup doesn't consider Routing Assigned Units on Routing
 
For a given Operation Sequence on both WIP and flow routing we have 5.5 units of the labor resource that we would like included in the item costing for the assembly. When the supply chain cost rollup program runs it only considers one of the labor resources in item costing despite the assigned units. 

EXPECTED BEHAVIOR
-----------------------
Expect the Labor to reflect the full quantity

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.