12.2.7 Batch Created From ASCP Release Start Date Is Not Correct (Doc ID 2412505.1)

Last updated on JUNE 18, 2018

Applies to:

Oracle Process Manufacturing Process Planning - Version 12.2.7 to 12.2.7 [Release 12.2]
Oracle Advanced Supply Chain Planning - Version 12.2.7 to 12.2.7 [Release 12.2]
Information in this document applies to any platform.

Symptoms

12.2.7
with GMPRELAB.pls 120.24.12020000.6

PROBLEM
-------------
Issue reported in bug 25690645 is not ported and released in 12.2

Customer has planned order with due date of 13-AUG
NEW_WIP_START_DATE 8/13/2018 18:58
NEW_SCHEDULE_DATE 8/13/2018 20:03

They change implement date to 01-AUG and release the order
WIP INTERFACE SHOWS
FIRST_UNIT_START_DATE 8/13/2018 18:58
LAST_UNIT_COMPLETION_DATE 8/1/2018 20:03

Batch is created with wrong start date

STEPS
--------
Update implement date for planned order
Release planned order to OPM

This works fine in our current 12.1.3 instance

Cause

To view full details, sign in with your My Oracle Support account.