My Oracle Support Banner

OPM Batch Plan Completion Date is before Plan Start Date (Doc ID 2414945.1)

Last updated on AUGUST 28, 2018

Applies to:

Oracle Process Manufacturing Process Execution - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

On Application Release 12.1.3:

ACTUAL BEHAVIOR
---------------

It was found that, for a batch, after batch has been rescheduled, the batch Plan Completion Date is earlier than the batch Plan Start Date.


EXPECTED BEHAVIOR
-----------------------
They are expecting to change the plan start date also in order to not become later than plan to complete

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1.Batch - Reschedule

BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Due to this issue, users cannot have correct completion dates

Changes

 No changes

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.