R12: Why Won't Custom Calculated Measures Populate In The Task And Resource Summary Pages?

(Doc ID 2419727.1)

Last updated on JULY 05, 2018

Applies to:

Oracle Project Planning and Control - Version 12.1.3 and later
Information in this document applies to any platform.

Goal

Custom calculated measures are not populating in the Task and Resource Summary pages.


Measure Type = Computed
Measure Source = Financial Plan Amounts
Measure Effort = Effort

How can the user get these to appear?

Solution