Resource Requirements Form, Shows Wrong Quantities Of Resource Applied And Open

(Doc ID 2421579.1)

Last updated on JULY 11, 2018

Applies to:

Oracle Work in Process - Version 12.2.7 and later
Information in this document applies to any platform.

Symptoms

On :  12.2.7 version, Transactions

After upgrade from 12.1.3 to 12.2.7, the Resource Requirement form shows a different value for the Applied resource.
In 12.1.3 the value was shown correctly in UOM MINUTES, but in 12.2.7 the value is shown in UOM HR (Hour) while all the other are correctly displayed

Expect to have a data consistency when displaying information. The data was not changed in the data base.

The issue can be reproduced at will with the following steps:
1. open Resource Requirement for job in question
2. observe different values

Cause

Sign In with your My Oracle Support account