My Oracle Support Banner

Batch Resource Transactions not Processed When API Calls Made Via ERES Events. (Doc ID 2422275.1)

Last updated on JULY 13, 2018

Applies to:

Oracle Process Manufacturing Process Execution - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

On : 12.1.3 version, Batches

ACTUAL BEHAVIOR
---------------
Resource transactions are not getting completed when batch is Completed.

EXPECTED BEHAVIOR
-----------------------
Resource transactions should be completed upon batch Completion.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:

1. Eres Event: oracle.apps.gme.batch.complete and/or oracle.apps.gme.batchstep.complete defined to call gme api synchronously.
2. Production supervisor -> Load wip batch to form.
3. Complete batch (This will kick off enabled eres events)
4. Steps form -> drill down to transactions and they seem to be not completed (completed_ind = 0). Actual_rsrc_usage at resource level is defaulted properly.


Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.