Symptoms

In Financial: Budgets and Forecasts > Maintain Forecast Versions > Edit Forecast >


Oracle is limiting the project from setting a date prior to current Actuals period date.
For this resource line and for this task there were no actuals in May, only prior to that.
The end date was 27-May-18.
User tried resetting it to 15-April and received above error.
The user is trying to change the Forecast Finish Date from 27-May to 15-April.

Note: The above are example dates to clarify issue.

 

Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.