Value Of The Last Progress Does Not Change The Entry Screen Of The Progress In The Assignments Tab. Why? (Doc ID 2453531.1)

Last updated on SEPTEMBER 28, 2018

Applies to:

Oracle Project Planning and Control - Version 12.2.5 and later
Information in this document applies to any platform.

Goal

Need to determine how much service was executed on a monthly basis for a customer in a specific project in order to be able to pay the service provider.

Contracted service: Dig a 1,000-meter ditch to place gas piping.

Therefore, a project was created with a task to execute this service.

An expense type was created, for example: "dig ditches", with "meters" as a unit of measure and a value for this cost.

This cost was placed in service in the resource planning list.

This resource was associated to the task in the project.

The information on how many meters were executed by the provider on a monthly basis to determine the value to be paid.

So, go to the project work plan and in the "actual this period" field entered the amount of meters that have been dug/executed. In the ETC field and updated the remaining amount.

These two field are enabled just to be filled manually when the project structure is "partially shared" and with the versioning activated in the work plan.

They are using partially shared projects so that it allows it to be manually updated of the progress in the resources assigned in the tasks of the work plan.

trying to rollup progress from the TeamMemberUpdateProgressPG page, but nothing gets rolled up as the as_of_date does not change to the current date.

Oracle Project Planning and Control User guide, page 3-91, states:

Oracle Projects creates a new progress record for the same As of Date when you correct
previously submitted progress. It also retains the previously published progress record.

When you correct progress, you can enter a progress status, a brief overview,
comments, physical percent complete, and actual quantity (non-shared structures only)
as long as no progress records exits with an As of Date after the As of Date for which
you want to correct progress. Otherwise, you can correct only the progress status and
physical percent complete. You cannot change the As of Date.

For example, if you previously submitted progress for 08-DEC-2004, you can choose to
correct the progress record at a later time. You can correct the progress status, physical
percent complete, and actual quantity (non-shared structures only) as long as no
progress records exist with an As of Date after 08-DEC-2004. You can correct only the
progress status and physical percent complete if progress records exist with an As of
Date after 08-DEC-2004.

Does the page not perform the rollup for entered data on this page?
 

Solution

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.