R12: Error "Budget cannot be entered at this task" When Update Forecast Cost Budget For Project (Doc ID 2472291.1)

Last updated on DECEMBER 21, 2023

Applies to:

Oracle Project Planning and Control - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

The budget entry method is Top Task, Lowest Task
The top task has a budget entered in another budget version and it has a sub task.
The sub-task also has a lower task under it.

When the user is trying to add budget for any of these tasks, the following error messages are displayed:

ERROR
-----------------------
Budget cannot be entered at this top task. A budget has been entered at a lowest task under this top task. Budget entry is restricted to top task or lowest task.
Budget cannot be entered at this task. Budget entry is restricted to top task or lowest task.
Budget cannot be entered at this lowest task. A budget has been entered at the top task of this lowest task. Budget entry is restricted to top task or lowest task.

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!