ACTUAL BEHAVIOR

When opening a calendar based PM schedule from the Activity Workbench the Data in the Tab called "Calendar Based" is not displayed although it is present.
However, when opening the same schedule directly in the PM Schedule definition form, this data can be seen.


EXPECTED BEHAVIOR

Calendar Based tab should display all data when the PM schedule is opened from the Activity Workbench.

STEPS

The issue can be reproduced at will with the following steps:
1. Responsibility: Enterprise Asset Management.
2. Go to Activity Workbench.
3. Create a new activity.
4. Launch Activity Workbench with asset and assign to the newly activity.
5. Go Preventive Maintenance -> Open PM Definition. PM Type = Rule Based.
6. Enter PM information. Use Schedule Type = Calendar Based.
7. Close PM schedule form and re-open the Activity Workbench.
8. Select the newly created activity and click on Preventive Maintenance, then click Open button.
9. From the above screen, the calendar based tab is NOT showing any data.
10. Now, close this form and directly open the PM Definition form.
11. The data is displayed when it is opened from the PM SCHEDULE DEFINITION FORM directly, BUT not when opening the PM Schedule from the Activity Workbench.

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.