Symptoms

ACTUAL BEHAVIOR
When project locator is set on WIP Material Transactions Header form, project cost group is used for WIP return transaction even though non-project locator is provided on transaction line form.

EXPECTED BEHAVIOR
Project cost group for sub-inventory is used.

STEPS
The issue can be reproduced at will with the following steps:

  1. Define Project Cost Group in Project Parameter form.
  2. Define bill for assembly and associate component which has the following attribute;
    Supply Type = Push
    Supply Locator = Non-Project locator
  3. Create a discrete job and associate project to it.
  4. Create WIP issue transaction for push component. It is pulled from non-project locator based on bill definition.
  5. On WIP Material Transaction header form, create WIP return transaction as below;
    Transaction Type: WIP Return
    Locator: Project Locator
    All Materials : Y
  6. On WIP Material Transaction line form, set non-project locator for component.
  7. Go to On-Hand Quantity form, and query component item. Then it is observed that project cost group is associated to the inventory.

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.