Symptoms
We are trying to creating a new Bill for a Planning item , when we enter the the component and then navigate to Component detail tab.
The Planning % field is not updable / greyed out.
Note when adding the component, the planning % defaults to 100 and we want to change it. The issue is only when we are creating a new Bill.
But once we save and then re-query we are able to update the planning %.
EXPECTED BEHAVIOR
Note when adding the component, the planning % should be editable and provide option to customer to change it
STEPS
1. Create a new item that has BOM Type as Planning and assign it to the apprppriate org.
2. Create a Bill. (Bill of Material Superuser > Bills > Bills, select an appropriate org).
3. Enter the item as the new planning item created.
4. At the line / Component level - add components.
5. Go to the Component details Tab and try to change the Planning %.
6. The field is greyed out.
7. A message appears below that the field cannot be updated with error: FRM-40200.
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Cause |
Solution |
References |