ACTUAL BEHAVIOR
---------------
Contract Negotiation Status remains in 'Draft' after it is Submitted for Approval from a Custom status defined under the 'Entered' status type

EXPECTED BEHAVIOR
-----------------------
Expect the Negotiation status to move to 'Awaiting Internal Response'

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1) Create a new Contract
2) Its current status is 'Entered' - 'Draft'
3) Use Change status form to change it to 'Complete' status
4) As per the 'Status and Operations' setup , 'Complete' is under 'Entered'
    status type
5) Contract current status is 'Complete' 'Draft'
6) Now Submit the 'Contract for Approval'
7) Contract status remains in 'Complete' 'Draft'
8) Click on 'Status Change' option from Tools menu
9) Cancel the Status change window
10) Observe contract status moved to 'Complete' 'Awaiting Internal Response'
11) Expected the contract to move to 'Complete' 'Awaiting Internal Response'
      when it was submitted for Approval and not after launching and closing
      'Status Change' Window.

Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.