My Oracle Support Banner

If WIP:DEFINE DISCRETE JOB FORM =Concurrent definition, Completion Date Is Not Moved (Doc ID 2568420.1)

Last updated on MARCH 12, 2021

Applies to:

Oracle Work in Process - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

Actual Behavior

The Saturday and Sunday are non working days and others are workind days. The profile option WIP:Define Discrete Job Form is set to Concurrent definition.
When attempting to create a discjrete job which completion date is on Monday 00:00:00, the completion date is not moved to Saturday 00:00:00 even though WIP: Align Job Dates with Shift Calendar=Yes.
The profile option WIP:Define Discrete Job Form is set to Interactive definition, the issue does not occur.

Expected Behavior
The completion date is moved to Saturday 00:00:00 sicne  WIP: Align Job Dates with Shift Calendar=Yes.

Steps to Reproduce

  1. Set WIP:Define Discrete Job Form=Concurrent definition and  WIP: Align Job Dates with Shift Calendar=Yes
  2. On Discrete Jobs form, create a discrete job with setting completion date on Monday 00:00:00 and save it.
  3. Ensure concurrent request 'WIP Concurrent Exploder' is completed.
  4. Query the discrete job.

Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution
References