Symptoms
In the Projects form:
While extending the Project Duration End Date from 1-DEC-2020 to 31-DEC-2027, get error:
"There are charged expenditure items in this project with
date later than the project end date. Please revise the end
date of the project to be same as or later than the
expenditure items' date."
Checked existing expenditure items but there is no such expenditure item exists.
No error occurs when the end date was given as 31-DEC-2028.
Cause
To view full details, sign in with your My Oracle Support account. |
|