My Oracle Support Banner

PAAPIMPB: PRC: Interface Supplier Costs Process Supplier Cost Interface Audit Report Shows Exception: 'New Transaction Creation not allowed for this project status' (Doc ID 2601869.1)

Last updated on JUNE 12, 2023

Applies to:

Oracle Project Costing - Version 12.2.6 and later
Information in this document applies to any platform.
PAAPIMP_SI: PRC: Interface Supplier Costs
PAAPIMPR: AUD: Supplier Costs Interface Audit

Symptoms

After successful completion of the PRC: Interface Supplier Costs concurrent program, the Supplier Cost Interface Audit shows the exception:


New Transaction Creation not allowed for this project status

 

STEPS TO REPRODUCE:

  1. Project Costing Responsibility > View > Requests > Submit a new request
  2. Run the concurrent program PAAPIMP_SI: PRC: Interface Supplier Costs
  3. On completion, observe the logfile and the Supplier Cost Interface Audit output

Changes

Issue occurs after upgrading to 12.2.6 or higher.  Starting in 12.2.6, there are additional validations enforced by the code introduced through Bug 26513494 - SUPPLIER INVOICES MATCHED TO PO CAN BE CHARGED TO CLOSED PROJECTS.

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.