Task Number Missing in Expense Report After Disabling Charge Flag for Task
(Doc ID 2615585.1)
Last updated on JULY 01, 2024
Applies to:
Oracle Project Costing - Version 12.2.4 and laterInformation in this document applies to any platform.
Symptoms
On : 12.2.4 version, Expense Report Flow
ACTUAL BEHAVIOR
---------------
Task Number is not appearing in Expense Report.
EXPECTED BEHAVIOR
-----------------------
Task Number should appear in Expense Report.
STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Go to iExpense responsibility.
2. Create expense report for specific task
3. Go to Project responsibility.
4. Open project form and query project number.
5. Disable Allow Charge flag for task against which expense is created.
6. Go to iExpense responsibility and review expense report created at step 2.
Changes
Cause