Symptoms


Oracle Product Workbench shows Project and task id instead of project and task names
 

EXPECTED BEHAVIOR
-----------------------

Oracle Product Workbench should show project and task names;


STEPS
-----------------------
The issue can be reproduced at will with the following steps:
Development Manager > Launch Product Workbench
See that product workbench is opened.
Search with item 'SMX_TEST4XX' and see the organization is selected as required organization
See the item results displayed
Click on "+" symbol and see the structure 'Root Primary' opened.
Double click on the 'Root Primary' structure.
Select the 'Structure Criteria' and change the display format to 'Material Control'
Enter the Sub inventory at component level under the parent item SM_TEST4
Sub inventory: Stores10xx
Now go to locator field and then do the following
Enter locator as 'ST1xx%'
See the locator results are not showing project name and task name, they are showing project id and task id



Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.