Preventive Maintenance (PM) Activity Suppression
(Doc ID 2632320.1)
Last updated on JULY 18, 2024
Applies to:
Oracle Enterprise Asset Management - Version 12.1.3 and laterInformation in this document applies to any platform.
Goal
Scenario is as follows.
I have defined 4 activities. Activity A which repeats in cycle needs to be suppressed by activities B, C and D if it falls within 3 days.
Right now the system is letting me suppressed only one activity which is B . For the other activities I am getting below error.
Violates the Suppression rule . One may Suppress many but one can only be suppressed by one.
A loop is detected in the Suppression relationship.
Is there functionality in Oracle that would allow to suppress activities B, C and D based on PM setup ?
Solution