ACTUAL BEHAVIOR
---------------
In the Service Request form > Task tab when assigning a task to a technician using assignment manager the gantt does not show the full day.  The Gantt only shows from the current time forward.

For example if the current time is 14:00.  The gantt starts at 14:00 instead of 00:00

EXPECTED BEHAVIOR
-----------------------
Users are expecting to see the entire day starting at 00:00

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Create a service request and task
2. In the Service request form > Task tab  select the 'Assignment manager' button to assign the task
3. The Gantt screen shows the timeline starting from the current time.


Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.