Symptoms
On : 12.1.3 version, Transactions
ACTUAL BEHAVIOR
---------------
OSP jobs not completed automatically after delivering the Qtys to the Shop Floor
EXPECTED BEHAVIOR
-----------------------
OSP job should be completed after delivering to the Shop Floor
STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Login to WIP (R)
2.Create OSP Job.
3.Perform Move to OSP Operation queue.
4.PO/PR Creation done.
5.Qty Received and Delivered to the shop floor.
6.Job still in status Released.