Oracle Property Manager - Version 12.1.3 and laterInformation in this document applies to any platform.
Symptoms
When attempting to change the Option status of a lease from 'Open' to 'Cancelled'
the following error occurs.
ERROR
-----------------------
PN_CANNOT_CANCEL_OPTION
STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Navigate to Lease Workbench
2. Query the lease
3. Navigate to the Options tab
4. Change the status from 'Open' to 'Cancelled'
BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Due to this issue, users cannot change the status of the Option
Changes
Cause