Symptoms

You have an assembly that has an outside processing operation at the first operation in your routing. The WIP Parameter is set so that a PO requisition is created for the OSP item when the discrete job for the assembly is released. When you create a discrete job for the assembly, no requisitions are created. Requisition Import is not launched and no records are inserted into PO_REQUISITONS_INTERFACE.

Cause