Incorrect Component Issued Quantity In Resulting Lot Based Job After Merging Multiple Lots (Doc ID 2708638.1)

Last updated on SEPTEMBER 08, 2020

Applies to:

Oracle Shop Floor Management - Version 12.2.4 and later
Information in this document applies to any platform.

Symptoms

On : 12.2.4 version, Lot Based Job

ACTUAL BEHAVIOR
---------------
Incorrect Component Issued Quantity in resulting lot based job after Merging multiple WIP lots in Queue intra-operation step

EXPECTED BEHAVIOR
-----------------------
Expect the component issued quantity to be correct

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Resp: Shop Floor Management
2. We start a job and then split it into 2 job lots and then consume components into separate jobs.
3. After merging these jobs into one, the issued quantity of component will not match actual consumed quantity



Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.