FORM:OKEKAUWB.FMB - Contract Authoring Workbench
FORM:OKECHGRQ.FMB - Contract Change Requests
FORM:OKEKAUWB.FMB - Contract Authoring Workbench

Goal

Question #1

=========

Is it possible approve a contract document manually without using Workflow?
Is there a manual way to approve the contract document (contract management).
Or, the contract document should start(be created) with a status 'Approved'.

How can they setup Project Contracts with a manual method to approve a contract without using workflow?
Or, how can they setup Project Contracts with a method to automatically set each contract to "Approved" on creation?


Question #2

=========

Is it possible to use the 'Change Management' functionality manually without using Workflow.
The pre-seeded workflow goes through the following statuses:
              Entered >> Submitted >> Approved >> Implemented >> Completed.
Is there a manual way to bring this status (change management) to Implemented without using Workflow?

How can they setup Project Contracts to accomplish this without using Workflow?

Solution

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms