Resource Calendar Is Showing Non Working Day In ASCP For Active Calendar
(Doc ID 2742776.1)
Last updated on NOVEMBER 21, 2022
Applies to:
Oracle Process Manufacturing Process Planning - Version 12.2.5 and laterInformation in this document applies to any platform.
Symptoms
On : 12.2.5 version,
ACTUAL BEHAVIOR
---------------
When looking at the Resource Capacity calendar in the Collections (and Supply Chain Planning) Workbench, after 28-AUG-2019, the Calendar is showing all dates as 'Non Working Time'
EXPECTED BEHAVIOR
-----------------------
These dates should show as 'Working Time' based on the calendar that is assigned via the Resource Information form in Process Engineering responsibility
STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Setup calendar and resource
2. Associate calendar with resource
3. Run collections
Changes
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Changes |
Cause |
Solution |
References |