Goal
PO receipt is not transferred to Projects because the Task End Date on the Project is earlier than the PO Receipt Date.
For example,
PO Receipt Date is dated as Mar-01-2021
Task End Date on the Project is dated as Feb-01-2021
Due to this date issue, the PO Receipt is not picked up to transfer to Projects when PRC: Interface Supplier Costs is run.
How can this be corrected?
Solution