My Oracle Support Banner

Update to Modifier Setup Errors with "The Date Range Of The Modifier Line Must Be Within The Date Range For The Modifier List" (Doc ID 2772444.1)

Last updated on APRIL 28, 2021

Applies to:

Oracle Advanced Pricing - Version 12 and later
Information in this document applies to any platform.

Symptoms

On : 12.2.9 version, Modifiers Setup only

When attempting to update the start date on the modifier list (header record) to a future date than original date,
the following error occurs.

ERROR

The date range of the modifier line must be within the date range for the modifier list.



STEPS

The issue can be reproduced at will with the following steps:

1. Responsibility: Oracle Pricing Manager
2. Navigate to: Modifier > Modifier Setup
3. Query modifier
4. Attempt to update the start date of the modifier header and save.
5. Error is shown:
  'The date range of the modifier line must be within the date range for the modifier list.'



WHAT DOES WORK
When same actions were taken in 12.1.3, an error message was not shown, even
if the header's new start date (aka 27-APR-2021) if after modifier line start date (24-APR-2021)



How this error may also occur

Customer copies current modifier list to a new modifier list whenever a price increase takes place.
For example, say a price increase occurs 1-MAY-2021.
They copy modifier A to a new modifier B where the new modifier B will have modifier (header) start date = 1-MAY-21.
This is needed to maintain prices for specific customers, attributes, etc.

Changes

 Recently upgraded to 12.2.9 from version 12.1.3

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.